Renewables developer GMR Power has began work on a 240 MW/480 MWh battery venture in Victoria, Australia.
From pv journal Australia
GMR Power is at present pursuing a 1.3 GW portfolio of storage initiatives throughout japanese Australia, albeit with a delayed timeline. The standalone 240 MW/480 MWh Mornington Battery Power Storage System (BESS), south of Melbourne, follows the corporate’s pivot from photo voltaic to storage round 2021.
The Mornington venture has secured improvement and connection approvals, and GMR Power CEO Morris Zhou says its accomplice, Victorian community AusNet, has begun early works and is buying one thing that has been within the lead for a very long time. To this finish, Zhou famous that disruptions within the provide chain have led to a “important bottleneck within the availability of transformers and different crucial supplies.”
AusNet will construct the transmission infrastructure required for the Mornington venture, positioned adjoining to AusNet’s current Tyabb substation. GMR Power mentioned it was additionally in “closing negotiations” with an engineering, procurement, and building contractor to construct the Mornington battery, though it was unclear which firm had received the contact.
The Mornington venture will depend on vitality arbitrage and frequency provide and grid management companies to generate income.
GMR Power has 5 different initiatives in its pipeline, together with 225 MW/450 MWh Gould Creek BESS in South Australia, which has additionally been granted permission for the event software. As well as, the corporate has lodged improvement functions for 3 battery initiatives in New South Wales, together with a 150 MW venture in Armidale, a 200 MW venture in Tamworth, and a venture of 100 MW in Lismore – all with two hours of storage. length.
pv journal print version
The newest difficulty of pv journal appears to be like at how the long-established hyperlink between photo voltaic and hashish cultivation may help enhance margins because the medicinal and leisure use of the drug strikes away from weed. We journey Down Underneath to analyze why communities are rebelling towards deliberate renewable vitality zones which are seen as being railroaded with out ample native session, and we contemplate the “photo voltaic crime ” wave sweeping the UK and Europe.
All of those initiatives will miss their unique completion dates, which the corporate had scheduled for this yr or final yr. It is value noting that the corporate appeared formidable in its preliminary timelines, typically predicting a yr between public bulletins and completion.
In Might 2022, the corporate publicly introduced its largest venture up to now, the AUD 1.6 billion ($1.06 billion) Merriwa Power Hubwhich features a 550 MW photo voltaic farm and a 400 MW/1,600 MWh battery vitality storage system within the Hunter area of New South Wales.