Australia’s largest electrical energy “gen-tailer” AGL is a step nearer to powering up its 250 MW/250 MWh grid-scale battery on South Australia’s Torrens Island after receiving the go-ahead from the Australian Power Market Operator.
From pv journal Australia
AGL’s $180 million Torrens Island battery power storage system is nearing business operation with South Australian electrical energy transmission community proprietor ElectraNet confirming it has executed a transmission connection settlement after to approve the efficiency requirements of the Australian Power Market Operator (AEMO).
The one-hour battery is being constructed on website at AGL’s gas-fired Torrens Island energy station and will probably be used to assist South Australia’s power transition, offering important capability when renewable technology is affected and during times of excessive demand.
“Full energy and commissioning actions for AGL’s Torrens Island battery will happen over the subsequent few weeks.” Electranet’s Buyer Connections Supervisor Niketan Tyagi mentioned.
“We’re offering important assist within the testing and commissioning of the auxiliary load on this undertaking pending the required efficiency requirements to be permitted by the Australia Power Market Operator and our staff.”
AGL’s undertaking director for battery, Thomas Hill, mentioned that the implementation of the connection settlement is a vital milestone for the power storage system, which may have a component within the expertise that varieties the grid and can initially focus to offer providers to the grid.
The battery, delivered by Finnish expertise firm Wärtsilä, will initially be sized at 250 MW and 250 MWh however enlargement plans permit for as much as 1,000 MWh, or 4 hours of storage capability.
“The Torrens Island battery is a vital asset, each for AGL’s portfolio and for the state of South Australia,” Hill mentioned.
“The battery will assist the uptake of higher ranges of renewable power, enhance the safety and reliability of the grid and assist put downward strain on electrical energy costs. It’s also a key pillar of our plan to relocate the Torrens Island website to an built-in, low-carbon industrial power hub.
The Torrens Island undertaking varieties a part of AGL’s ambition to have 5 GW of recent renewables and renewables in place by 2030, increasing a 2.9 GW pipeline of renewable technology and power storage tasks in energetic planning and growth.
Among the many firm’s different power storage tasks are a 200 MW, four-hour grid-scale battery to be constructed on the Loy Yang An influence station website in Victoria, and a 500 MW/2 GWh battery within the close to future. closed the Liddell energy station in New South Wales.
It acquired a mark of approval from NSW planning authorities for a 50MW/100MWh battery in Damaged Hill, and It introduced a take care of the Maoneng Group to purchase capability from 4 50 MW/ 100 MWh battery in NSW and already working at 100 MW. /150 MWh Wandoan South battery in Queensland and the 30 MW/8MWh BESS at Dalrymple in South Australia.
This content material is protected by copyright and will not be reused. If you wish to cooperate with us and need to reuse a few of our content material, please contact: editors@pv-magazine.com.