On the request of the developer, a public listening to for 2 Yakima County photo voltaic farm tasks scheduled for Tuesday night time was postponed by officers of the state’s Power Facility Web site Analysis Council.
The web assembly, the place EFSEC will hear displays from employees, developer Cypress Creek Renewables and the general public on the Excessive High and Ostrea proposals, will likely be rescheduled to a future date, the company introduced Monday morning.
Yakima County commissioners not completely satisfied state company OKs photo voltaic farms
The postponement got here after the California-based developer requested that the time-frame for state officers to contemplate the venture’s website certification be prolonged till February 22.
“This request is particularly for an extension of processing time for the EFSEC advice to the Governor for approval and signature,” Tai Wallace, Cypress Creek’s senior director of improvement, wrote in a letter dated November 18 to EFSEC supervisor Sonia Bumpus. The letter was posted on-line by EFSEC on Monday morning, Nov. 28.
“By way of discussions with EFSEC employees, we discovered the time of the general public conditional use allow assembly on the finish of November, the cancellation of the December assembly attributable to vacation schedules, and the present deadline for the Governor’s choice which at the moment falls earlier than the EFSEC council assembly in January ends in the necessity for the present deadlines to be adjusted,” Wallace wrote.
“Whereas we hope {that a} advice from EFSEC and a choice by the Governor will occur within the first quarter of 2023, we additionally need to give sufficient time to all events and businesses to assessment the applying, coordinate the mitigation request, and may conduct requested evaluations and approvals at usually scheduled EFSEC council employees conferences.
Cypress Creek Renewables is searching for approval for 2 80-megawatt photo voltaic farms on State Route 24, about 20 miles east of Moxee. The Excessive High and Ostrea websites cowl practically 1,600 acres every, with photo voltaic panels and different gear deliberate for 613 and 908 acres, respectively, nearly fully north of the state freeway.
They’re separate tasks as a result of they are going to be served by two totally different energy traces: Excessive High on PacifiCorp’s Union Hole Halfway 230 kV transmission line, and Ostrea on the Bonneville Energy Administration’s Moxee to Halfway 115 kV transmission line.
Earlier this month, the EFSEC board unanimously authorized an order granting expedited processing to Cypress Creek Renewables. It requires adjudicative proceedings and allow evaluations for close by photo voltaic tasks to be scheduled inside 60 days. If EFSEC approves the permits, its advice will likely be despatched to Governor Jay Inslee for remaining approval.
The Yakima County Board of Commissioners protested the expedited processing. They despatched EFSEC officers a letter on November 7 asking the state company to carry off on approving any further photo voltaic farm tasks till native rules for setting them up are in place. County Planning Officer Tommy Carroll despatched EFSEC officers the same letter on Nov.